ARCO, Calexico

August 22nd, 2012 by Fiedler Group

Fiedler Group was retained by AVEN Design to assist in the development of an ARCO gas station and convenience store on an undeveloped 1.6 acre parcel located along Highway 111 in California’s Imperial County. Read the rest of this entry »

Arco ampm

June 10th, 2011 by Fiedler Group

Various locations

In 2005, Arco embarked on a program to sell company-owned facilities to its franchisees. A vital component of this transition was the seamless design and permitting of each respective site’s adaptation of ampm’s brand.

Leveraging our firm’s storied history in successful tenant improvement and program rollout — as well as an extensive knowledge of both building and environmental health code, Fiedler Group successfully designed and permitted 151 store retrofits throughout California, Arizona, and Nevada utilizing a scope of services including:

  • existing site measurements,
  • as-built drawings,
  • development of the equipment plan,
  • creation of construction documents, and
  • acquisition of all required permits.

Contact us today to learn how we can help you with your project!

Arco AMPM

Arco AMPM Arco AMPM

NEXT: See other examples of our convenience markets expertise. Learn more >>

Arco ampm

June 8th, 2011 by Patrick Fiedler

Various locations

In 2005, Arco embarked on a program to sell company-owned facilities to its franchisees. A vital component of this transition was the seamless design and permitting of each respective site’s adaptation of ampm’s brand.

Leveraging our firm’s storied history in successful tenant improvement and program rollout — as well as an extensive knowledge of both building and environmental health code, Fiedler Group successfully designed and permitted 151 store retrofits throughout California, Arizona, and Nevada utilizing a scope of services including:

  • existing site measurements,
  • as-built drawings,
  • development of the equipment plan,
  • creation of construction documents, and
  • acquisition of all required permits.

Contact us today to learn how we can help you with your project!

Fiedler Group Supports Iwatani’s Roll-Out Of Hydrogen Fueling Stations Despite Covid

April 28th, 2023 by Fiedler Group

1. Intro Photo

Fiedler Group was contracted by Iwatani Corporation of America (ICA) to perform the multi-site program known as Futurity. Fiedler Group services included both Front-End Engineering and Design (FEED) and Engineering, Procurement and Construction (EPC) services for six (6) light duty hydrogen fueling facilities in existing retail petroleum stations located in Anaheim, Corona, Hawaiian Gardens, La Mirada, Santa Ana, and Seal Beach, California. Despite the processing delays experienced during the time of Covid, Fiedler Group had all project sites designed, permitted and constructed in record time. ICA selected NEL Hydrogen to supply the integrated hydrogen fueling system for the program.

As the Engineer of Record for the Futurity Program, Fiedler Group provided design expertise and technical oversight on each project. FEED services included delivering preliminary conceptual designs to ensure site viability; entitlement processing with the completion of Site Investigation Reports to evaluate capability and capacity for site development as well as barriers to execution; and engineering and design sets for permitting and AHJ review. Furthermore, Fiedler Group provided continuous construction management support during the design phase to ensure constructability and expediency during construction. Fiedler Group selected Fastech for the construction of all six locations.

HAWAIIAN GARDENS

The first of six projects to be completed for ICA was co-located at an existing 76 gas station. The site at 11807 E. Carson Street, Hawaiian Gardens, CA was enhanced with a hydrogen fueling station that included two fuel dispensers supported by an equipment compound holding the storage and compression equipment required to operate the dispensers.

2. Hawaiian Gardens

Fiedler Group saved our client a significant amount of costs by presenting to the AHJ options to eliminate design requirements for additional water lines and service. The initial requirement included an irrigation water meter for the planned landscape area. However, Fiedler Group designed the Landscape Water Efficiency Plan to intercept the water line on the private property and use the existing meter for both irrigation and domestic service.

Construction of the hydrogen fueling facility was completed on October 22, 2021, with an approximate construction duration of 4 months.

SEAL BEACH

The second Futurity project to be completed for ICA was co-located at an existing 76 gas station. The site at 13980 Seal Beach Blvd. Seal Beach, CA was enhanced with a hydrogen fueling station that included two fuel dispensers supported by an equipment compound holding the storage and compression equipment required to operate the dispensers.

This project was another Fiedler First, as we were given the opportunity to design and construct the first hydrogen station in the City of Seal Beach. Fiedler Group’s extensive experience in bringing new fueling solutions to cities allowed us to anticipate the jurisdiction’s concerns and resolve them to facilitate entitlement and permit processing.

One of the challenges presented involved the restrictions against modifying the existing canopy. Fiedler Group’s solution was to design and construct a canopy “spanner” which provided the client the opportunity to showcase their logo and hydrogen branding.

3. Seal Beach Canopy
4. Seal Beach

Construction of the project was completed on February 17, 2022, with an approximate duration of 6 months.

ANAHEIM

The third Futurity project to be completed for ICA was co-located at an existing Mobil gas station. The site at 1100 N. Euclid Street. Anaheim, CA was enhanced with a hydrogen fueling station that included two fuel dispensers supported by an equipment compound holding the storage and compression equipment required to operate the dispensers.

5. Anaheim

One of the challenges Fiedler Group overcame on this project was the management of stakeholders to energize the site. This process was a milestone in the construction of these sites and required careful coordination. Fiedler Group collaborated with all parties to have the site energized after normal working hours, thereby ensuring that the project schedule was not impacted.

The Anaheim project was completed on April 15, 2022, with an approximate construction duration of 5 months.

CORONA

The fourth Futurity project to be completed for ICA was co-located at an existing Mobil gas station. The site at 616 Paseo Grande, Corona, CA was enhanced with a hydrogen fueling station that included two fuel dispensers supported by an equipment compound holding the storage and compression equipment required to operate the dispensers.

The Corona site had several unique obstacles. During the Preliminary Phase, Fiedler Group discovered that the site had various conflicting and outdated recorded property lines that impacted the constructability within the proposed location of the equipment compound and canopy. Fiedler Group was retained to ensure that a Lot Line Adjustment was granted. A Lot Line Adjustment is an extensive process that involves altering the property lines of existing parcels of land. Fiedler Group successfully obtained a Certificate of Compliance granting the adjustment that included the merging of a Lot that had been acquired by the City via annexation from the County. In addition, we successfully obtained a release of an existing but unused utility easement on the property returning 74 feet of land to the site owner, while also providing a third access point to the site, and clean Title to the property.

6. Corona

The hydrogen fueling facility was completed on June 24, 2022, with an approximate construction duration of 5 months.

SANTA ANA

The fifth Futurity project to be completed for ICA was co-located at an existing Shell gas station. The site at 2120 E. McFadden Ave. Santa Ana, CA was enhanced with a hydrogen fueling station that included two fuel dispensers supported by an equipment compound holding the storage and compression equipment required to operate the dispensers.

7. Santa Ana Aerial

Fiedler Group was able to reduce the entitlement and permitting schedule significantly by preemptively communicating with the City’s Planning Department to address any concerns and expedite an administrative review of the proposed project. Fiedler Group facilitated the extensive negotiation process to have easement documents modified and accepted by SCE, the site owner, and the neighboring property owner for the installation of new electrical equipment, as well as acceptance of transformer use on a neighboring property.

8. Santa Ana

Once preconstruction issues were mitigated, the site was completed on July 7, 2022, with an approximate construction duration of 5 months.

LA MIRADA

The sixth Futurity project to be completed for ICA was co-located at an existing ARCO gas station. The site at 13550 S. Beach Blvd., La Mirada, CA was enhanced with a hydrogen fueling station that included two fuel dispensers supported by an equipment compound holding the storage and compression equipment required to operate the dispensers.

9. La Mirada

This site had one of the most interesting utility challenges we have had the opportunity to resolve to date. During the Preliminary Phase of the project a few challenges were discovered: (1) the existing gas station’s electrical transformer also served power to the neighboring Fire Station, (2) the existing gas station and the Fire Station were in two different jurisdictions, and (3) the same city that owned the Fire Station also owned an easement on the gas station property that conflicted with the proposed location of the equipment compound. The primary obstacle to the project was that, regardless of the solution, the Fire Station could not be without power for any amount of time. Therefore, after extensive research and negotiation with relevant stakeholders, Fiedler Group successfully resolved to have SCE provide the Fire Station with independent power lines and transformer.

The La Mirada project site was completed on December 21, 2022, with an approximate construction duration of 7 months.

To learn more about Fiedler Group and the services we provide, please contact us today.

7-Eleven Expands Bill Payment Opportunities in New York

November 7th, 2017 by Fiedler Group

The New York City Department of Finance recently announced that they have partnered with financial services technology company PayNearMe to let NYC drivers pay for parking tickets in cash at more than 100 7-Eleven convenience stores in all five boroughs. Read the rest of this entry »

$6.4 Billion Tesoro Acquisition of Western Refining Announced

November 22nd, 2016 by Fiedler Group

Tesoro Corporation and Western Refining, Inc. have announced a definitive agreement where Tesoro will acquire Texas based Western.  Read the rest of this entry »

GasBuddy App Names Low-Price Retail Fuel Winners

January 26th, 2016 by Fiedler Group

After combing through over 650-million price submissions, GasBuddy selected low-price retail fuel winners. Read the rest of this entry »

Clean Energy Fuels, Perris

May 5th, 2015 by Fiedler Group

Clean Energy Fuels Corp. just completed construction and are in the final commissioning phase of a liquefied natural gas (LNG) fueling facility in Perris, CA. Read the rest of this entry »

Clients

July 26th, 2013 by Patrick Fiedler

 

Alternative Fuels Clients

BP Architecture Engineering Chevron architecture engineering Clean Energy architecture engineering
Hyundai architecture engineering Iwatani Shell architecture engineering
SoCal Edison architecture engineering socalgas architecture engineering toyota-architecture-engineering

 


 

Retail Petroleum Clients

Arco Architecture Engineering BP Architecture Engineering Chevron architecture engineering
ConocoPhilips architecture engineering ExxonMobile architecture engineering Shell architecture engineering
Tesoro architecture engineering texaco architecture engineering Ralphs architecture engineering
Food 4 Less architecture engineering Foods Co architecture engineering vons architecture engineering
Circle K architecture engineering SC Fuels architecture engineering DeWittIPS architecture engineering

 


 

Food Service Projects

aw architecture engineering baskin robbins architecture engineering carls jr architecture engineering
cowboy burgers architecture engineering del taco architecture engineering ihop architecture engineering
jack in the box architecture engineering Mcdonalds architecture engineering pizza hut architecture engineering
sonic-architecture-engineering sonoma-coffee-architecture-engineering Subway architecture engineering
Subway architecture engineering taco bell architecture engineering taco time architecture engineering
tcby architecture engineering Wienerschnitzel architecture engineering  

 


 

Convenience Store Clients

711 architecture engineering AMPM architecture engineering Arco Architecture Engineering
Couche-Tard architecture engineering Circle K architecture engineering extra mile architecture engineering
famima architecture engineering on the run architecture engineering starmart architecture engineering

 


 

Retail/Commercial Clients

CVS architecture engineering family-dollar architecture engineering kaiser-permanente-architecture-engineering
west coast choppers architecture engineering

 


 

Government/Utilities Clients

CHP-architecture engineering City-of-Los-Angeles- architecture engineering City-of-Montebello architecture engineering
City of Pasadena architecture engineering ladwp architecture engineering
long beach transit architecture enginerring SoCal Edison architecture engineering socalgas architecture engineering

 

Kroger Fuel Sales Tops Big-Box Retailers in Latest NACS Retail Fuels Report

March 5th, 2013 by Fiedler Group

The National Association of Convenience Stores recently released their 2013 NACS Retail Fuels Report summarizing the current status of the U.S. Petroleum Industry. Read the rest of this entry »